Santos outlines GLNG progress to date

An artist’s impression of the GLNG Project.

An artist’s impression of the GLNG Project.

Approximately 100 km of the 420 km mainland pipeline right-of-way has been cleared and graded, 70 m of pipeline has been strung, and 1,000 joints have already been welded.

At a recent investor seminar, Santos stated that a peak workforce of 1,300 is expected on the pipeline by April 2013, with the pipeline to reach completion by the second quarter of 2014.

&++++ !++!++ #!+ ++ !++!++#+ #+ ++ !++!++ #+!+. &++++ !++!++ !# ++. ++ !++!++ #+!+. &++++ !++!++ !# ++. ++ !++!++ #+!+. &++++ !++!++ !# ++. &++++ !++!++ ! ++ !++!++#+ #+ ++ !++!++ #+!+. &++++ !++!++ #! ++. ++ !++!++#+ #+ ++ !++!++ ##+!+. &++++ !++!++ !# ++. #+ ++ !++!++ #+!+. &++++ !++!++ #! ++.

&++++ !++!++ #!+ ++ !++!++#+ #+ ++ !++!++ #+!+. &++++ !++!++ !# ++. ++ !++!++ #+!+. &++++ !++!++ !# ++. ++ !++!++ #+!+. &++++ !++!++ !# ++. &++++ !++!++ ! ++ !++!++#+ #+ ++ !++!++ #+!+. &++++ !++!++ #! ++. ++ !++!++#+ #+ ++ !++!++ ##+!+. &++++ !++!++ !# ++. #+ ++ !++!++ #+!+. &++++ !++!++ #! ++.

&++++ !++!++ #!+ ++ !++!++#+ #+ ++ !++!++ #+!+. &++++ !++!++ !# ++. ++ !++!++ #+!+. &++++ !++!++ !# ++. ++ !++!++ #+!+. &++++ !++!++ !# ++. &++++ !++!++ ! ++ !++!++#+ #+ ++ !++!++ #+!+. &++++ !++!++ #! ++. ++ !++!++#+ #+ ++ !++!++ ##+!+. &++++ !++!++ !# ++. #+ ++ !++!++ #+!+. &++++ !++!++ #! ++.